Major works starts on Monday 31st July to replace a large section of gas pipeline under Chester Road, Helsby, which is essential to keeping homes in the area warm.
Cadent, which manages the local gas network, is calling time on a section of its pipeline that runs directly under the A56, between Helsby High School and the junction with Primrose Lane – which is a distance of some 3,200 metres.
The work will be completed in phases and the road will stay open, with traffic lights controlling the flow of vehicles around the specific area being worked in.
Old metallic gas mains like these are being upgraded as part of an £800m investment by Cadent in its North West network over five years. In April, Cadent revealed its programme for 2023/24 included around 418km of upgrades in the North West.
As well as keeping homes warm today – more than 80 per cent of local homes have gas central heating – this programme is helping to get the network ready for a move away from fossil gases to hydrogen, which is essential for a ‘net zero’ future.
Records indicate that some sections of this pipeline were installed in the early 1940s. They are now showing signs of its age – with repairs and maintenance, and associated traffic disruption, increasing in frequency in recent years.
Mark Syers, Head of Investment Planning Office (North West), Cadent, said: “Our job is to keep gas flowing to heat homes, schools, offices and many other buildings in the local area, as well as future-proof the network ready for hydrogen.
“This part of the network has operated for more than 80 years. We’ve become too frequent a visitor in recent years, with our teams carrying out essential repairs.
“This upgrade will bring an end to that, ensuring everyone gets a safe, reliable supply well into the future.
“We appreciate this means another period of disruption and will maintain a work area that ensures the road can stay open, albeit with traffic lights.”
As well as the larger diameter main in the road, the engineers will also replace the individual ‘service’ pipes that carry gas into some properties. Work is also taking place in a number of streets that lead off Chester Road.
The start point, near Helsby High School, has been deliberately scheduled for the summer holidays, to minimise disruption here.
Gas stays ON.
The Cadent teams will ensure gas stays ON throughout the project. This is apart from one day, as each property’s supply is connected into the new main. Advance notice will be given, and gas will be restored the same day it goes off.
When does it start – and how long will it take?
Teams will move in to start the project on 31st July. The programme of work is likely to continue through to the end of the year.
Inserting most of the new pipe into the old pipe = reduced disruption
For around 80 per cent of the project, the engineers will use a technique of inserting the new plastic main into the old metallic main. This reduces the number of excavations needed and therefore reduces the timeline of the project.
Contacting Cadent about this project
Customers with questions about this work can contact the team by:
Phone: 0800 090 3071
Email: CustomerCareNW@cadentgas.com
Online: https://cadentgas.com/contact-us/contact-form-nw
If you smell gas
If you smell gas during this work, nearby or anywhere, always ring the national gas emergency service immediately, day or night, on 0800 111 999*. Do not delay, or assume it is related to this work. It may not be and must be checked.
Cadent in the North West
Cadent’s ‘North West’ network covers a wide area that includes Cheshire, Merseyside, Lancashire, Greater Manchester, Cumbria and parts of Derbyshire.
Beneath this region – under roads, footpaths and fields – are more than 34,000km of gas distribution pipes. These carry gas to 2.7 million homes, hospitals, schools, offices and other sites – for heat, hot water, cooking and industrial uses. If placed end to end, they’d reach Sydney, Australia, and come back again.
Cadent manages this extensive network, as well as gas networks for Eastern England, West Midlands and North London. It is responsible for ensuring the network is operating safely and reliably, 24/7, 365 days a year.
Cadent will invest more than £3.4bn over the next five years (including more than £800m in the North West area) to maintain this network and get it ready for the arrival soon of greener, low-carbon gases, such as hydrogen.
Blues Match Report: Merthyr Town 1 - 2 Chester FC
Blues Match Preview: Merthyr Town v Chester FC
Chester and Wirral Football League - Weekend Round Up
AWARD-WINNING COMEDY TO BE STAGED AT CHESTER LITTLE THEATRE
Cabinet to defer decision on schools’ reorganisation proposal
Local MP Justin Madders joins Gavin & Stacey star Alison Steadman to back Marie Curie appeal
Make Your Food Go Further this Food Waste Action Week
Council launches campaign to recruit more Shared Lives carers
Men sentenced in connection with Cheshire West drug supply
19TH CENTURY "GIRL POWER" SET TO BE CELEBRATED AT CHESTER CONCERT
Blues Match Report: Chester 2 - 1 Darlington
Blues Match Preview: Chester FC v Darlington
Councillors urged to throw out proposals to merge four catholic schools
Man jailed following Ellesmere Port phone robbery
Charlie’s 20‑mile challenge brings joy to young patients at the Countess of Chester Hospital
Local MP Marks World Book Day and Champions National Year of Reading Across Chester North & Neston
Chester Racecourse donates £10,000 to fund Storyhouse Skills Studio
Comments
Add a comment